What a Factory Acceptance Test should cover

A Factory Acceptance Test is the last opportunity to find problems cheaply. Here is what a meaningful FAT for power equipment includes.

ASTERON Engineering

Power equipment is far easier to correct in the factory where it was built than on a site thousands of kilometres away. The Factory Acceptance Test — the FAT — exists to make sure problems are found while that is still possible.

Why test at the factory

At the factory, the people who built the equipment, the drawings, the spare components and the test facilities are all in one place. A wiring error or a wrong setting can be corrected in hours.

On site, the same problem can stop commissioning while parts and specialists travel. For projects in remote locations, that difference can be measured in weeks.

Start with the procedure

A meaningful FAT follows a written procedure agreed in advance. The procedure is derived from the project specification and states, for each test, what will be done, what result is acceptable and how it will be recorded.

Without an agreed procedure, a FAT tends to become a demonstration of what works rather than a verification of what was specified.

What is checked

The content depends on the equipment, but a FAT for power generation equipment generally includes:

  • Visual and dimensional inspection — construction, finish, labelling and dimensions against the approved drawings.
  • Component verification — the components fitted match the approved list.
  • Wiring and insulation checks — terminations, continuity and insulation resistance.
  • Functional tests — controls, alarms, protection and interlocks operate as specified.
  • Load testing — for generator sets, running under load through defined steps while performance is recorded.
  • Interface tests — signals and communication with other equipment in the system behave as the design requires.

For plants with several generator sets, synchronising and load sharing can often be demonstrated where the test facility allows it.

Punch lists and release

Not everything passes first time, and that is the purpose of the exercise. Open points are recorded on a punch list, with responsibility and completion criteria for each. The equipment is released for shipment only when the points that affect function or safety are closed and verified.

The signed test report, with its records, becomes part of the project documentation.

Attending a FAT

Owners and their representatives are entitled to witness the test, and attending is worthwhile. It is an opportunity to see the equipment operate, to meet the people who built it, and to confirm that what will arrive on site is what was ordered.

If attending in person is not practical, an independent engineer witnessing on your behalf — with a clear procedure and a documented report — provides the same assurance.

Related

Continue exploring

Manufacturing & Quality

Factory Acceptance Testing

Formal, witnessed testing of equipment against the specification before it is released for shipment.

Manufacturing & Quality

Load Bank Testing

Running generator sets under load at the factory to verify performance, stability and protection.

Manufacturing & Quality

Quality Assurance

A project-specific quality plan defining what is checked, when, by whom and against which criteria.

Start with your load

Tell us about your load. We’ll engineer the system.

Share what you know about your project — even if some of it is still undecided. Our engineers review every inquiry.

No price lists. Every proposal is engineered to your project.